Act A - The Market Structure
A public school is usually built for a fixed sum. The owner signs a stipulated-price contract with a general contractor. The general contractor signs fixed-price subcontracts with the trades. Each trade then buys its material over the next two or three years at whatever the price is on the day.
Statistics Canada reported that non-residential building costs rose 12.5 per cent in 2022, the largest annual increase since that index began. A move of that size can be larger than a small trade's margin on the job.
The Canadian Construction Association publishes an example escalation clause for the standard prime contract. Its bulletins also say that the protection often stops at the prime contract, and that a trade facing too much risk should not bid.
So trades pad their bids or stay away, and owners pay for the padding or receive fewer bids. The trade usually cannot see the prime contract, so it cannot tell a job with shared risk from one without.
The following is a fictional account of how a marketplace built on DeeperPoint's design could close this gap.
Act B - The Story
Renata runs a twelve-person electrical firm in Brandon, Manitoba. Two years ago she wired a recreation centre at a fixed price. Copper rose after she signed. She finished the job and made nothing on it. Since then she has bid only on work that finishes within six months.
She describes her firm to the marketplace in her own words: commercial and institutional electrical work, crews for jobs up to eighteen months, copper wire and cable as the cost she cannot control, and a rule that she will hold a price for ninety days and no longer unless the contract adjusts for copper.
Colm estimates for a general contractor in Winnipeg that is bidding on a school addition in western Manitoba. The owner's tender includes a price-adjustment term for a short list of materials, copper among them, tied to a published index with a threshold. Colm has two electrical prices so far. He suspects both carry a cushion for copper. He uploads the tender's general conditions and his firm's subcontract form, and adds one line: the firm will pass the owner's adjustment term down to the trade unchanged.
The marketplace reads the documents into a profile and matches it against the trades' descriptions. Renata and Colm each receive the same Content Match Story. Neither is named in it. It says that an electrical contractor within reach of the site will take on an eighteen-month job where copper is adjusted by index, and that a general contractor bidding such a job will pass that term down. It states plainly what is not yet known: the threshold, and whether the trade's bonding covers a job of this size.
Both agree to be introduced. Renata sees the clause itself for the first time. She prices the job at current copper cost, with no cushion. Her number is the lowest of the three. A Deal Brief sets out the adjustment term, the index, the notice period and the records she must keep, for her lawyer and her surety to review.
Act C - Why This Market Stays Broken Without Infrastructure
The clause existed before Renata saw it. What was missing was any way for her to learn, before spending a week on an estimate, that this job came with it.
The marketplace took no risk in this story. The index clause did that work, and the owner who wrote it did. The platform's part was to make the terms part of what is matched, and to keep each side's numbers private until both chose to talk. That is the role thin-market infrastructure plays when a market fails on information and not on supply.
Renata, Colm, their firms and the school project are fictional. The cost figures from Statistics Canada and the Canadian Construction Association's guidance on escalation clauses are real. Risk insulation is designed and not yet built, and the story does not rely on it. DeeperPoint is building the infrastructure this story describes.